Maintenance Dredging

28May2015

Maintenance Dredging

Please be informed that today, 28/05/2015,  preparations for the maintenance dredging of the harbour mouth will commence.  The dredging itself will commence on  29/05/2015 and will last a maximum of 15 days if weather conditions permit.

The recovered sands, via a floating pipe to the south of the Sotogrande beach, will be deposited a few metres to the north of the river Guadiaro mouth mole, thereby contributing to the stabilizing of the same.

Buoys and markers will indicate both on the beach and in the water the procedures  being carried out.  In order to maintain the security conditions, we would appreciate your attention to the same.

We do apologise for any inconvenience that these works may cause to users of the beach and harbour.